Housing for All ? Status Report



Business Line ( 10 Sept 2016 ) carries a news report , titled :

"  Housing for All in the slow lane "



Following are its highlights :

#  " Housing for All " mission was launched in June 2015 , to construct 200 Lakh houses by 2022

#   As of date, construction of 9 lakh houses has been approved by the Ministry of Housing

#   Of these , some 72,000 houses are under construction across 7 states

#   So far , only 2,883 houses have been completed ( 1719 in Gujarat / 718 in Chhattisgarh / 446 in Tamil Nadu )


#   Out of 36 States plus UT , 15 have not even sent their proposals to the Ministry !



At this rate , by  2022 , expect following :

#    5 Lakh ....  under construction

#    25,000.... completed

#      5,000 .... allotted



Having raised the EXPECTATIONS of poor people of India , it is still not too late for Shri Narendra Modi  to ask, Niti Aayog to re-frame the " HOUSING  FOR  ALL "  mission along the following lines :


QUANTUM JUMP OF 50 MILLION HOUSES    

 

   {  http://myblogepage.blogspot.in/2016/02/cheap-houses.html  }

 

*   A  Half  Way  House

 

 {   http://myblogepage.blogspot.in/2016/01/a-half-way-house.html  }

--------------------------------------------------------------------------------------------------------------------------